THE SHORT ANSWER

Keep a dated record for each proposed extra or omitted item. Write down the agreed scope, any change to price and VAT, the effect on timing and who approved it under the contract. Keep payments in a separate ledger against milestones. Check the running contract total and evidence of completed work before paying each invoice.

Regional note

This guide is written for United Kingdom. Always check local codes, product specifications, licences, and site conditions. Browse the United Kingdom edition.

Preparation

Start with the signed work and payment schedule

Use the accepted scope as the baseline for changes. Keep the original document alongside any later versions to preserve the record of what was agreed.

  • Write down the contract total, VAT basis, signed drawings and agreed dates. Record any provisional sums or allowances separately.
  • List who can approve a change and the notice or approval process described in your contract.
  • Make a payment register containing invoice number, milestone, invoiced amount, amount paid and the date.
The method

Step by step

01

Open a change record as soon as a difference appears

Ask the contractor for a written description of what has changed and why. Record the affected room, drawing, and the reason, whether this is an owner request, a newly discovered condition or a product change. Photos help a person who was not on site understand what appeared. Ask whether the proposal replaces existing contracted work, adds to it or removes part of it. Where there is uncertainty about what the original quote covered, put that question into the record. The term extra can hide a genuine change or reprice something that was already included. Use the actual contract and independent advice when needed. Keep emergencies and safety decisions with the competent person managing the work.

02

Get both time and money confirmed

For a proposed change, ask for any revised labour, material and access costs and the same VAT basis used in the contract. Ask what would be credited if a previously priced item comes out. Record what the builder can quote firmly and what remains an estimate. Ask how the sequence changes for other trades and any required inspection. Check whether an approval, design or landlord condition requires revision before authorising affected work. Ask for the option of quoting a clearly scoped alternative when time allows. In the agreed record include any effect on the finish, revised completion milestone and whether the new work changes what records must be handed over.

03

Check a worked variation against the running total

An illustrative accepted kitchen refit totals £9,600 on an agreed VAT-inclusive basis. You request a tile trim change costing £180 and remove a shelf installation for an agreed credit of £120. Record those as separate entries with their reasons and the same invoice basis. The agreed total is then £9,660, assuming no other changes. If payments to date add up to £5,200, the running unpaid contract balance is £4,460. The next invoice is still due only according to the contract’s terms and the applicable milestone. Keep the balance separate from a list of things still to decide. An estimate for a possible future change belongs in the forecast, and should not be counted as approved.

04

Compare invoices to the log and raise differences promptly

Check that a billed milestone or change can be traced to the agreed evidence. If one work stage includes multiple items, make sure the reference and documentation identify the right stage. Keep receipts and record whether deposits are credited against particular payments. Ask about differences with specific references and screenshots rather than a broad objection. Use the contract, Citizens Advice for the relevant UK nation or independent help if disagreements remain. A generic payment register cannot decide whether a payment should be withheld. At close out, reconcile every paid amount with the final account, schedules, agreed changes and remaining items, then copy the records to your home project file.

Before you start

Expert tips

  • Use one identifier for each change, such as V03, throughout the scope, written approval and invoice. The record should explain the decision from start to finish.
  • Add credited and omitted items with the same care as additions. Check that an old version of the accepted scope cannot accidentally be issued to the site team.
  • Mark disputed entries clearly and keep evidence and correspondence beside them. A marked entry prevents its inclusion in a clean list of approved changes while preserving the record of what each side has said.
People also ask

Common questions

Can a builder charge extra for something I asked them to change?+

Additional work you request can affect the price. Ask how it is priced and recorded under your agreement. The terms, accepted information and evidence matter if a dispute arises.

Do I pay the full remaining contract balance when the next invoice arrives?+

Check the relevant milestone or due date against your agreed payment schedule. An outstanding balance helps with budgeting while the contract determines the amounts that are due and when.

Primary references

Sources & further reading

We link to official building-code, government and public-health material where a technical or safety claim needs authoritative context. Local rules and adopted code editions can change.

  1. Citizens AdviceBefore you get work done on your homeEngland consumer guidance on written quotes, contracts and paying for home improvements.
  2. legislation.gov.ukConsumer Rights Act 2015, servicesPrimary law on consumer contracts for services, including reasonable care and skill.
  3. Citizens AdviceProblem with building work, decorating or home improvementsEngland consumer guidance on documenting and resolving issues with a trader.
!
Know your limit

Stop if the work involves structural uncertainty, hazardous materials, heights, live services, gas, serious water damage, or regulated work. Local rules differ—use an appropriately licensed professional where required.