Multiply the net area by the supplier’s installed pavers per square metre, add your cutting allowance once and round up to whole pavers. Divide that result by the supplier’s units per pack and round up again. Record the two numbers separately so you can see how much surplus comes from buying full packs.
Use the paving and pack calculator
This guide is written for South Africa. Always check local codes, product specifications, licences, and site conditions.
Step by step
Measure the paved footprint
Sketch the finished edge before walking around with a tape. Mark everything that should stay open, including planted beds and inspection covers. Split a simple L-shape into rectangles that touch without overlapping. Write dimensions in metres beside each rectangle and multiply length by width before combining the areas. If a border uses a different paver, measure its area as a separate item so it does not appear in both totals. On a sloped or irregular site, confirm the measurement method with the installer before committing to an order. Record the sketch date so a layout revision does not quietly change your shopping list.
Use the exact supplier product
Ask for a written product code, installed coverage and units per pack or pallet. Two products sold as the same nominal size can use different laying dimensions or have a different pack count. If coverage is quoted in square metres per pack, ask whether that area includes the recommended joint and whether the pack contains mixed sizes. Keep the published information beside your written quote. A face-area calculation is useful early in planning because you can do it without a product code. Use the supplier’s stated installed coverage when ordering a specific product, and check whether it already includes a waste allowance.
Apply allowance before pack rounding
Decide how much extra to allow with the person who will lay the job. A straight rectangle with full units at the edges may create fewer cuts than a curved path or diagonal pattern. Reusable cuts depend on the shape, pattern and whether the cut edge can be hidden. Enter the allowance as a separate percentage so you can revise it without remeasuring. Count any loose samples separately. When the supplier sells only full packs, round up the required pavers first and then round up the pack count. Keep the surplus shown by that second calculation separate from the pieces allowed for cuts.
Work through a 24 square metre order
Suppose your net area is 24 square metres, your product specification gives 49 pavers per square metre, and you have agreed a ten per cent allowance. The calculation is 24 multiplied by 49 and then by 1.10, which gives 1,293.6. Round up to 1,294 pavers. With 100 per pack, 12 packs leave you short and 13 give you 1,300. The six extra pavers come from pack rounding alone. This is a worked example, so substitute the actual coverage and pack size on your order. Confirm whether the border, steps or a different colour require a separate order.
Check delivery and keep a record
Ask whether the supplier will split packs, how returns work and whether coloured stock from the same production batch can be reserved. Include delivery and unloading when comparing prices. Full pallets are heavy and the supplier should confirm access and a suitable offloading point. When the order arrives, check labels and obvious damage before installation starts. Set aside useful whole units if there is space to store them safely. A note of the product code, colour, purchase date and laying pattern will help if the surface needs a repair later. Save the worksheet with the quote and delivery paperwork.
Expert tips
- The pack count covers the wearing surface. List edging, jointing sand, bedding and any base materials separately from the paver order.
- Confirm drainage, base preparation and traffic suitability before committing to a product. The same count can apply to a footpath and a driveway even when the construction specifications differ.
Common questions
Can I use 50 pavers per square metre?+
It is the raw face-area count for a 200 by 100 millimetre rectangle. Use the supplier’s installed coverage for the exact product when placing the order.
Can I buy one pack less if the result is close?+
Check whether the supplier sells the shortfall as loose units. An order below the calculated requirement leaves less than the agreed allowance.
Should I include a few spare pavers after the job?+
Keeping sound full units can help with later repairs. Count those separately if you want a dedicated reserve after installation.
Sources & further reading
We link to official building-code, government and public-health material where a technical or safety claim needs authoritative context. Local rules and adopted code editions can change.
Stop if the work involves structural uncertainty, hazardous materials, heights, live services, gas, serious water damage, or regulated work. Local rules differ—use an appropriately licensed professional where required.