THE SHORT ANSWER

Draw the board runs, use the installed board width and specified gaps, and count the rows across the deck. Check how to finish the last row before ordering. Convert the rows to stock lengths from an approved cut layout rather than dividing deck area by board area alone.

Regional note

This guide is written for South Africa. Always check local codes, product specifications, licences, and site conditions.

The method

Step by step

01

Confirm what part of the deck receives boards

Sketch the finished surface and note borders, stairs, ramps and transitions. Measure the width across the intended boards and the length along them. Mark sections that need a different profile or direction. Ask the deck installer to confirm usable dimensions and edge details before counting, particularly at doors or where site levels differ. This is an order estimate for boards, not a design for framing or footings. Make sure the selected product and support system are appropriate for the deck and its environment. Keep anything requiring separate materials on its own line so the same area does not appear in both counts.

02

Use the actual product width and installation rules

Read the manufacturer’s current guide for board width, fixing system and spacing. Side gaps, end joints and perimeter clearances may be different values. Do not substitute a generic gap or assume a hidden fastener creates the correct spacing for a different product. Confirm how the product permits cut edges and last-row fixing. Board width stated in a listing can describe the full profile rather than the exposed surface, so ask which measurement belongs in your setout. Record the actual width, side gap and any clearances in millimetres. Discuss expansion, ventilation and drainage with the installer before working out the order.

03

Calculate rows with an example

Say the usable width after perimeter clearances is 2,850 mm, an illustrative board is 140 mm wide, and the system specifies a 5 mm gap for this example. Nineteen full boards plus 18 gaps occupy 2,750 mm. Twenty full boards plus 19 gaps take 2,895 mm. If the selected system allows the last piece to be cut and supported appropriately, the twentieth row would need a 95 mm board strip plus its preceding gap. Check the arithmetic from both edges and confirm the final row arrangement before buying. Some systems or layouts need the whole setout adjusted rather than trimming one board to suit the leftover.

04

Turn row lengths into a stock and cut list

Write the length of each board run. If a run is longer than the available stock or needs a join, ask where joints can be placed on the approved framing and how they must be fixed. A spare piece is usable only if it meets the product limits, length and joint arrangement. Mark stairs, edging and borders as separate parts with their own fixing details. If considering two stock lengths, compare how many pieces can be cut from each after allowing for the saw kerf and necessary end trimming. Review the plan to avoid counting one offcut for two locations. Add the agreed order allowance after the layout is final.

05

Confirm the order with the installer and record the product

Check batch or colour information, transport lengths and where stock will be stored safely. Ask which clips, screws, finishing boards or other accessories belong to that product rather than treating all systems the same. Review how the first and last boards are fixed and how joins will be checked during installation. Record the finished dimensions and actual materials so a future repair can match the installation. If the delivered product or dimensions differ from the quote, repeat the setout before cutting. A few spare pieces of compatible stock can be useful when the product is discontinued, provided there is suitable storage and a genuine need.

Before you start

Expert tips

  • Keep the board estimate separate from the structural design. Framing, support and approvals require the actual system and site checks.
  • Confirm the allowed narrowest cut and finished edge detail before relying on a ripped last board.
People also ask

Common questions

Do I include a gap after the last board?+

Count gaps between adjacent boards separately from required perimeter clearance. Use the product guide for both.

Can I use the same calculation for timber and composite?+

The geometry is similar, but the board widths, spacing, fasteners and joint details depend on the selected system.

Should I order by square metres alone?+

Compare square metres with a row and stock-length cut plan. The cut plan reveals joins and unusable surplus.

Primary references

Sources & further reading

We link to official building-code, government and public-health material where a technical or safety claim needs authoritative context. Local rules and adopted code editions can change.

  1. Eva-Last South AfricaDecking installation guidesCheck the reference alongside the current requirements for the exact product, property or installation.
!
Know your limit

Stop if the work involves structural uncertainty, hazardous materials, heights, live services, gas, serious water damage, or regulated work. Local rules differ—use an appropriately licensed professional where required.